Day 84 - 26/1/14
Well, the roof is pretty much complete now, and waiting for the Colourbond.
We have had some big issues over the last week or so, and we are working through them.
These include:
- No provision for the large Aircon Unit in the roof. So Engineers are now reworking the trusses, or we may have to redesign the roof... not good.
- The cavity slider in the master bedroom WIR has been put in the wrong way, so we now have no where to hang the plasma. Looking at options
- A joist runs right through the laundry chute
- A joist runs through where the projector lift is meant to go
- There is so little roof cavity space, that once the aircon is installed with all the ducting and droppers, there is not much point in a manhole, as you will not be able to move anywhere. Note to self for next time, make the roof higher.