Monday, 3 February 2014

Day 92 - 3/2/14


Had our SS come onsite today and lookover the following issues:
  • Office window is too low for the desk we are installing, and they need to fix it
  • Look at the trusses for the aircon
  • Look at the projector lift install
  • Decided to re-do the master cavity slider to resolve the plasma mounting issues. 
All roof trusses are now on (Garage and alfresco were not on until today), except for a bit around the back that the truss guys forgot to make.  Oops.